CLER LKE – KONOCTI6 60.0 kV (ckt 1)

Transmission line · 60 kVInternal gridDAM
CAISO ID: 31334_CLER LKE_60.0_31338_KONOCTI6_60.0_BR_1 _1

Current shadow price

Loading live market data…

Observed congestion

Peak shadow price
$1040.27
on 2026-10-27 at 15:45 UTC
Binding intervals
312
recorded in retained history
Tracked since
2026-07-24
105 days of observation

About this constraint

CLER LKE – KONOCTI6 60.0 kV (ckt 1) is a transmission line operating at 60 kVthat appears as a congestion constraint in the California ISO market. When power flow reaches this element's operating limit, CAISO's market optimization assigns it a shadow price — the cost to the system of that limit binding — which in turn drives locational price separation around it.

Across the market intervals retained in this dataset, it has bound 312 times, with the largest shadow price observed at $1040.27/MWh on 2026-10-27. Prices are shown with the sign CAISO publishes; magnitude is the severity signal.

Data comes from CAISO OASIS (PRC_NOMOGRAM) for both the day-ahead and real-time markets, refreshed automatically. This page is informational only and is not trading, financial, or operational advice.

Related internal constraints

OMS_21156170_SCE_PSPS_EXP
peak $9446.51 · 6 binding
17700_DIB_RGD
peak $1601.98 · 5 binding
HPLND JT 60.0/115 kV transformer (bank 2)
peak $26.09 · 1 binding
HPLND JT – CLVRDLJT 60.0 kV (ckt 1)
peak $332.23 · 184 binding
INYOKN nomogram
peak $972.90 · 294 binding
KONOCTI6 – EGLE RCK 60.0 kV (ckt 1)
peak $73.30 · 5 binding