MC FRLND – WASCO 70.0 kV (ckt 1)

Transmission line · 70 kVInternal gridDAM
CAISO ID: 34930_MC FRLND_70.0_34932_WASCO _70.0_BR_1 _1

Current shadow price

Loading live market data…

Observed congestion

Peak shadow price
$115.00
on 2026-08-28 at 01:00 UTC
Binding intervals
6
recorded in retained history
Tracked since
2026-08-07
35 days of observation

About this constraint

MC FRLND – WASCO 70.0 kV (ckt 1) is a transmission line operating at 70 kVthat appears as a congestion constraint in the California ISO market. When power flow reaches this element's operating limit, CAISO's market optimization assigns it a shadow price — the cost to the system of that limit binding — which in turn drives locational price separation around it.

Across the market intervals retained in this dataset, it has bound 6 times, with the largest shadow price observed at $115.00/MWh on 2026-08-28. Prices are shown with the sign CAISO publishes; magnitude is the severity signal.

Data comes from CAISO OASIS (PRC_NOMOGRAM) for both the day-ahead and real-time markets, refreshed automatically. This page is informational only and is not trading, financial, or operational advice.

Related internal constraints

OMS_21156170_SCE_PSPS_EXP
peak $9446.51 · 6 binding
INYOKN nomogram
peak $972.90 · 294 binding
ORO LOMA – POSO J1 70.0 kV (ckt 1)
peak $6.95 · 1 binding
LOS BANS 70.0/230 kV transformer (bank 3)
peak $173.86 · 68 binding
BORDEN 70.0/230 kV transformer (bank 1)
peak $22.93 · 1 binding
BORDEN – CASSIDY 70.0 kV (ckt 1)
peak $737.78 · 3 binding
← Back to the CAISO Congestion Monitor