Most congested transmission constraints in CAISO

Congestion in the California ISO market shows up as a shadow price on a specific piece of equipment — a transmission line, a transformer, or an operating nomogram. This page ranks those constraints two ways: how often each one binds, and how hard it hits when it does. The two lists are not the same, and the difference is usually the interesting part.

281 constraints tracked · 47 day observation window · data through 2026-09-05

Binds most often — internal grid

Ranked by the number of market intervals in which each constraint was binding.
1HPLND JT – CLVRDLJT 60.0 kV (ckt 1)Line · 60 kV · peak $820.28790
2EL CAJON – LOSCOCHS 69.0 kV (ckt 1)Line · 69 kV · peak $1842.38642
3OMS_19695948_DEV_RDB_ALISNomogram · peak $-131.45541
4LE GRAND – ADRA TAP 115 kV (ckt 1)Line · 115 kV · peak $915.67477
5INYOKN nomogramNomogram · peak $-1544.32466
6SNJQJCT – GFFNJCT 70.0 kV (ckt 1)Line · 70 kV · peak $169.35389
7TAFT – Q356TAP 70.0 kV (ckt 1)Line · 70 kV · peak $170.39375
8KRAMER – VICTOR 230 kV (ckt 2)Line · 230 kV · peak $300.95343
9USWP-WKR – SBTAP 60.0 kV (ckt 1)Line · 60 kV · peak $138.84339
10KETTLEMN – GATES 70.0 kV (ckt 1)Line · 70 kV · peak $200.35325
11SC21ATP – ARVIN 70.0 kV (ckt 1)Line · 70 kV · peak $3016.00303
12AEC_TP1 – TESLA 115 kV (ckt 1)Line · 115 kV · peak $1402.43290
13KINGSBRG – CONTADNA 115 kV (ckt 1)Line · 115 kV · peak $1193.94280
14TL649A OVERLOAD nomogramNomogram · peak $-1000.00239
15TL 230S OVERLOAD nomogramNomogram · peak $-757.09225
Counts are binding intervals observed by Voltlas within the retained history window, across both day-ahead and real-time markets.

Highest shadow price reached — internal grid

Ranked by the largest shadow price observed, in dollars per megawatt-hour.
1OTAY – OTAYLKTP 69.0 kV (ckt 1)Line · 69 kV · 23 binding intervals$4016.62
2PENDLETN – SANLUSRY 69.0 kV (ckt 1)Line · 69 kV · 69 binding intervals$1250.37
3MIDWAY – BELRDG J 115 kV (ckt 1)Line · 115 kV · 13 binding intervals$3910.24
4SANYSDRO – OTAY TP 69.0 kV (ckt 1)Line · 69 kV · 6 binding intervals$3800.63
5WESTPARK – KERN PWR 115 kV (ckt 1)Line · 115 kV · 30 binding intervals$192.26
6INYOKN nomogramNomogram · 466 binding intervals$-1544.32
7SC21ATP – ARVIN 70.0 kV (ckt 1)Line · 70 kV · 303 binding intervals$3016.00
8BORDER – OL649 69.0 kV (ckt 1)Line · 69 kV · 4 binding intervals$2591.62
9AEC_TP1 – TESLA 115 kV (ckt 1)Line · 115 kV · 290 binding intervals$1402.43
10115kv MLNomogram · 14 binding intervals$2074.64
11EL CAJON – LOSCOCHS 69.0 kV (ckt 1)Line · 69 kV · 642 binding intervals$1842.38
12NORTECH – NORTHERN 115 kV (ckt 1)Line · 115 kV · 3 binding intervals$1514.99
137690-COOLWATER_KRAMER_IM_NGNomogram · 144 binding intervals$-1259.69
14SylmarBNK N-S Import nomogramNomogram · 1 binding intervals$-1481.26
15NWARK EF 115/230 kV transformer (bank 11)Transformer · 115 kV · 15 binding intervals$1475.97
Values are shown with the sign CAISO publishes; ranking uses magnitude. A single severe hour can outrank a constraint that binds far more often.

Interties — binds most often

Scheduling constraints on the paths connecting CAISO to neighbouring grids.
1DOSMGO-PNOCHE_230_2_1Intertie · peak $760.521102
2LDWP_IPP_NORTHIntertie · peak $-327.82893
3IPPUTAH_ITCIntertie · peak $-191.45627
4PACW_COI_IMPORT_ITCIntertie · peak $-27.00302
5TEPC_BA_EXP_ITCIntertie · peak $-49.12294
6PACW_CRAG_ITCIntertie · peak $-1000.00266
7CASCADE_ITCIntertie · peak $-1000.00233
8SUNZIA_ITCIntertie · peak $-197.47206
9IPPDCADLN_ITCIntertie · peak $-12.59193
10PATH_14Intertie · peak $1487.44161
Intertie and internal counts are not directly comparable — the two feeds retain different history windows.

How to read these rankings

Frequency and severity measure different risks. A constraint that binds in most hours at a few dollars per megawatt-hour is a chronic, predictable feature of the network — it shapes where power is worth producing, but rarely surprises anyone. A constraint that binds twice a month at $4017 per megawatt-hour is the opposite: mostly invisible, then briefly dominant. Traders, schedulers, and planners tend to care about different ends of that spectrum.

Voltage is a useful second signal. Lower-voltage elements — 60, 69, 70, and 115 kV lines — appear frequently in the severity ranking because they serve local load pockets with limited alternative paths, so a single outage or a hot afternoon can push them to their limit. Higher-voltage 230 kV and 500 kV constraints bind less often but move much more power when they do.

Method and limitations

Rankings are built from CAISO OASIS market results (PRC_NOMOGRAM for internal constraints, PRC_CNSTR for interties), collected automatically and refreshed on this page weekly. They reflect what has been observed since tracking began — a 47-day window, not CAISO's full history, so a constraint that was severe last winter will not appear until it binds again. Internal and intertie counts come from feeds with different retention windows and should be compared within a section, not across them. Constraint names are parsed from CAISO's identifiers, so substation abbreviations follow CAISO's conventions. This page is informational only and is not trading, financial, or operational advice.